Tarrant County Water Supply Project | TRA | Euless, TX
RAVA Construction was awarded the Tarrant County Water Supply Filter Rehabilitation and Improvements Project by the Trinity River Water Authority of Texas. The project—located in Euless, Texas—had a contract value of approximately $32.2 Million.
The contract included rehabilitation of an 87 MGD water treatment plant regionally providing treated water service to a population of approximately 245,000. RAVA rehabilitated the existing 24 dual media filters; replaced underdrains, media, and wash troughs; and constructed a new chlorine contact basin. Likewise, the project included structural work, improvements to the filter gallery, Plant Control System upgrades, instrumentation and SCADA modifications, replacement of Caustic Feed Pumps, construction of chemical containment trenches, and installation of new chemical piping at various locations throughout the plant site.
Project was substantially completed July 2025.